August 31, 2013

Road work begins Tuesday on Abutment Road

Submitted by Dalton Public Works

— Maintenance work and asphalt patching is scheduled to begin Tuesday on Abutment Road in Dalton.

This work is in preparation for the resurfacing project scheduled to begin later in the month. The project includes 2.27 miles of resurfacing on two sections of Abutment Road beginning at Walnut Avenue and ending at Industrial Boulevard and also from the recently completed Callahan Road intersection project to the South Dalton Bypass.

Motorists should expect single lane closures and interruptions in traffic while the work is being completed as well as active work zones throughout these sections of Abutment Road. Motorists should reduce their speed and exercise caution while driving in these work zones.