FACT CHECK: Deal mistaken on nuclear plant costs

ATLANTA — Gov. Nathan Deal claimed last week that environmental litigation was running up the construction costs of a nuclear power plant in Georgia, despite abundant evidence to the contrary from the utility building it and an independent state monitor.

The Republican governor is a longtime supporter of the nuclear power industry. He made the remark last week just before Southern Co. executives gave their first public testimony since announcing the utility needed another $737 million to build two reactors at Plant Vogtle (VOH’-gohl), raising the project budget to $6.85 billion. That cost is ultimately paid by the utility’s customers, unless state regulators object.

A reporter asked Deal about the rising costs on July 16, shortly before the state’s Public Service Commission started a hearing on the utility’s spending.

“Well, you know, there’s an irony to that,” Deal said. “That is, the people who are in fact involved in costing through the litigation process then become the ones who complain about the cost of the litigation being initiated. There’s something a little bit unusual about being able to be the parties that are involved in running up the costs and then, on the other hand, complain about the costs themselves.”

But the utility and regulators most closely involved say licensing, production and construction problems have caused delays and increased costs, not legal challenges.

Stephen Smith, executive director of the Southern Alliance for Clean Energy, has fought the project legally and called Deal’s comments “factually inaccurate and inflammatory rhetoric.”

The Southern Co. utility, which owns 46 percent of the new reactors, has not cited litigation as a cost driver in its recent filings and testimony. It would have an incentive to blame environmental groups if litigation resulted in delays and major costs.

Delays are a tremendous concern for utilities building nuclear plants. If construction takes longer than expected, the interest charged on borrowed money and other costs stack up, producing a big bill for utility customers.

Environmentalists have challenged the project over river dredging and nuclear waste storage issues, for example, though none of their objections raised before the U.S. Nuclear Regulatory Commission ever prompted an order that halted licensing or stalled construction work. In May, a federal appeals court ruled against environmentalists who wanted to stop the NRC from approving new nuclear plants until the agency completes its review of a 2011 nuclear meltdown in Japan. Locally, groups have also sued to block Southern Co. from making its customers pay for the project’s finance charges before the new reactors start producing electricity.

Deal spokesman Brian Robinson said those lawsuits cause delays, but Southern Co. has never cited them as a factor when its officials testify under oath about why construction schedules have slipped. Robinson also said he believed Deal was speaking more generally about environmental lawsuits targeting the power industry, though Deal’s answer does not suggest he was addressing larger issues.

Rather than litigation, Southern Co. said delays were caused by a longer-than-expected federal review process, trouble implementing its design and difficulties getting a manufacturer to produce large parts on time and while meeting strict quality control rules.

One big delay was self-inflicted. Workers installed metal bars in a reactor foundation in ways that differed from the original design. While federal officials ultimately accepted those bars as safe, the approval process held up major construction work for months.

A nuclear engineer hired by the state to monitor construction, William Jacobs Jr., warned in a December report that he is concerned one lawsuit could cause delays and extra costs, though it is unrelated to environmental concerns. Rather, the plant’s owners and project contractors are suing each other over which firms are responsible for roughly $930 million, mostly in additional licensing costs.

———

Associated Press writer Jaime Henry-White contributed to this report. Follow Ray Henry on Twitter: http://twitter.com/rhenryAP.

 

1
Text Only
State News
  • One charged in death of Dalton woman, another sought

    A Dalton woman found dead in Calhoun earlier this month is believed to have died of a drug overdose after two Calhoun residents abandoned her in a car behind the VFW on East Line Street, Lt. Tony Pyle with the Calhoun Police Department said Wednesday afternoon.

    June 18, 2014

  • Guard shot at FedEx center to undergo 14th surgery

    A security guard critically wounded when a gunman went on a rampage at a FedEx facility is scheduled to undergo his 14th operation Tuesday.

    May 27, 2014

  • Arson ruled out as cause of chemical plant fire

    Police say investigators have been able to rule out arson or foul play as the cause of a massive fire at a chemical plant outside Atlanta that spewed black smoke and flames visible for miles.

    May 27, 2014

  • Teen tied to shopping cart drowns in lake

    Georgia Department of Natural Resources officials say a teen has died after being tied to a shopping cart and pushed into Lake Allatoona.

    May 25, 2014

  • Underground tattoo artists frustrate officials

    The work of tattoo artists whose living rooms double as body art studios might come cheap, but experts say the unsterile -- and illegal -- work environments could leave clients in pain long after the initial sting of the needle subsides.

    May 25, 2014

  • No runoff lets Republicans focus on Rep. Barrow

    While Georgia Republicans have to wait until July to settle runoff races for the U.S. Senate and three open House seats, one of the biggest GOP victories in the primary elections last week went to Augusta businessman Rick W. Allen.

    May 25, 2014

  • Audit probes juvenile justice turnover rate

    A state audit cites low pay, long hours and management concerns as reasons for a relatively high turnover rate at the Georgia Department of Juvenile Justice.

    May 25, 2014

  • Atlanta schools ex-tech director to be sentenced

    After his relationship with the superintendent of Atlanta’s school system soured, a former technology director for the district set up a kickback scheme to pad his pockets before he left his job, according to court documents.

    May 24, 2014

  • Georgia veteran, 92, honored at surprise ceremony

    Family and friends surprised a 92-year-old World War II veteran from Georgia on Memorial Day by honoring him and presenting him with the World War II Victory Medal.

    May 24, 2014

  • Police: Massive chemical plant fire extinguished

    Authorities say a massive fire at a chemical plant outside Atlanta that spewed black smoke and flames visible for miles has been extinguished.

    May 24, 2014